Wednesday 3 November 2010

Good Morning


Matt here, this morning has gave us a realisation of what a mountain we have made ourselves to climb. We're nackered basically, but we're going ahead with it anyways. Our problems this morning consist of...


El numéro one : Our keystones are smaller than planned and we do not have a correct amount of timber sections (2 sections we are minus)


El numéro two : We don't have a drill to drill a hole in the concrete foundations for threaded rod to hold this blissfully interesting thing up.


El numéro three : We don't have enough threaded rod to put into the concrete foundations.


El numéro four : The timber sections we are gluing and bolted together are extremely heavy and will be hard to transport to the site as we are fixing the whole structure into 4 different parts. Each being a half of an arch. 


El numéro five : To put the arch up we need scaffolding...guess what we don't have, yep scaffolding.


El numéro six : Time, time is precious. I wish we had more.